Adding Value Prior to Lease Execution

19 09 2013

The ink on the lease is still wet and the parties learn that the costs for improving the leased space far exceeds the tenant improvement allowance, or the landlord’s budget for turnkey delivery. Immediately, fingers are pointing as though they’ve been run through the meat grinder. It’s crazy how often this situation occurs, whether the real estate and construction advisers and participants are rookies or wily veterans. What’s the remedy?

A significant common factor among the successful real estate practitioners who’ve established client loyalty and are rewarded with repeat business, is the compilation of a reliable team of service providers (design, legal, furniture, teledata, construction, etc.). Surround yourself with willing, responsive partners and deliver a product that sets you apart from the average competition. Are you going to settle for average? Why should your clients? 

From the construction perspective, it’s vital to understand the exposure to you and/or your client related to the issues surrounding programming, design and construction. As a former office leasing professional, I can attest to the value of understanding the worse case scenario when negotiating the terms of a lease. 

As an end user, involving a general contractor early in the site selection and programming phase can help uncover certain building deficiencies, or excess costs associated with construction in certain buildings. The astute GC will provide feedback on electrical and mechanical capacity, potential code compliance shortfalls, life safety issues, and many other components that could help determine the short list of options in the marketplace. 

The building owner or landlord is well-served by engaging the GC early in the process to understand how quickly the space can be delivered in order to realize rental income; what code changes are looming that could affect construction costs; where mechanical or electrical distribution could exceed the prorata capacity associated with the space; and, to provide a realistic construction budget and schedule such that a turnkey delivery does not go over budget. 

Regardless of which side of the table you sit, it’s smart business to arm yourself and your team with as much knowledge as possible to tilt the scales of negotiation in your favor.

Typical services include touring existing or proposed space, whether for remodel or full build from shell; offering conceptual budgeting for tenant or capital improvements; defining realistic occupancy schedules; work letter review and negotiation; and conceptual scope definition. 

  • Comprehensive budget process
  • Project estimating
  • Value engineering
  • Site selection & feasibility
  • Project scheduling
  • Product research & recommendations
  • Cost segregation & life-cycle costing
  • Multi-dimensional Building Information Modeling (BIM)
  • Forecasting based on historic experience 

 





Scheduling Guidelines for Office Relocation

19 05 2010

Business expanding? Contracting? Lease expiring within the next two years? In the market for new office space? If so, this information could be quite useful. The following outlines the typical process and related timing expectations for planning your office relocation. There are extraordinary circumstances in most cases that tend to affect the “typical” process; so this should not be viewed as gospel, only a conceptual outline.

As an example, let’s assume that the use is a 20,000 square foot office user in an urban market with no extraordinary space or fit-out requirements. There are critical milestones to identify to achieve desired occupancy dates through the critical path method of project scheduling.

Milestones

  • Programming – The process in which the design team surveys the tenant’s (often referred to from a contract perspective as the “owner”) business practices, uses of space, flexibility in growth and contraction, and desired culture in order to determine the conceptual minimum space required.
  • Identify Adequate Office Space – The owner’s real estate professional (broker or consultant) will identify the available space in the marketplace that fits within with the program, location and economic parameters.
  • Create Short-List of Real Estate Options – The total inventory of feasible options is reduced to a manageable short list in an effort to create a competitive environment for securing one of the desired short list properties.
  • Develop Test-Fit Plans – The design team will create a test fit for the short-listed properties to ensure that the program as identified will fit the available space. Often times, it’s this process that uncovers certain inefficiencies of a building’s footprint that may eliminate it from contention. On the other hand, if a footprint is extremely efficient, the resulting program may indicate the opportunity to commit to less square footage, increasing the economic desire of that location.
  • Obtain Preliminary Construction Budgets and Schedules – Once the test fit plans (or, preliminary space plans) have buy-in from the owner, the contractor will provide preliminary estimates (often referred to as “budgets”) and the associated construction schedules for owner review and compare. This practice allows the owner to gain a greater understanding of its total financial exposure for various occupancy alternatives, a key component to the lease negotiations for the owner and the broker.
  • Conduct Lease Negotiations – The information provided by the design and construction teams will arm the brokers with the data necessary for an apples-to-apples comparison of the alternatives. There are generally two elements involved in the negotiation, the financial terms and the legal terms; the process of negotiating much of the key points (mostly financial or business terms) in the letter of intent (LOI) is one that can expedite the process and reduce legal fees.
  • Pursue Final Design, Permitting and Construction – As the short list is reduced to one, the process begins to develop the construction documents (CD’s), to pursue the permit process, and for the contractor to bid the final documents to the sub-trades in an effort to maintain a competitive final estimate. This component of the process may be shortened significantly via the collaboration of the design and construction team on behalf of the owner. See the discussion about the Design Build Project Delivery for Tenant Improvements for further discussion of the benefits of working as a team.
  • Substantial Completion of Construction – The point when construction is sufficiently complete in accordance with the construction documents, that the tenant (owner) can occupy the building or space. Typically, the architect or engineer will certify that the space is deemed “substantially complete”, which date becomes the date of substantial completion. The significance of this date is that it’s often a trigger for rent or term commencement per the lease – another point of negotiation that should be considered by the broker during the pre-construction phase.
  • Installation of Furniture, Fixtures & Equipment (FF&E) – The owner’s furniture, fixtures and equipment are moved in and installed. A prudent business practice is for the design and construction team to be actively involved with the various vendors in the early stages in order to avoid potential code or installation issues, which could become costly occupancy delays.
  • Commissioning and Certification of the Premises as Pertinent – With typical office space, the commissioning and start-up procedures are minimal when compared with that of mission critical facilities. However, although the magnitude of the owner’s teledata requirements might not be that of a 500MW data center, it doesn’t do the owner any good if their server room isn’t functioning as designed. There may also be a LEED Certification process that might require off-gassing of new materials prior to occupancy, for example. The related professionals should be consulted during the pre-construction phase in order to determine the time allocated for this final phase before occupancy.
  • Occupancy – Substantial completion has been achieved; all inspections have been successfully completed and signed off, the authorized agencies have issued a certificate of occupancy where necessary, and any commissioning processes have been completed, the owner may occupy.

In order to maximize leverage in lease negotiations, and minimize the unnecessary costs of expediting design, permitting and construction, Greg Fogg, Managing Director at Jones Lang LaSalle, suggests beginning the initial process about one year prior to the target occupancy date of the new premises.

“The caveat”, Fogg states, “is if a tenant has a renewal option that is relevant, requiring exercising one year prior to expiration… in that instance, we would likely trigger the early stage of our process (vetting the market) sooner so that the tenant is ready to make an educated decision by date of exercise.”

Before the brokers are able to accurately represent the user’s requirement in the market place, and as a prudent business exercise, the tenant should engage the services of a design firm to identify the actual size of the space needed. A common mistake is for an executive committee to give early directive about space needs without consulting a design professional. As an example, a 20,000 square foot user takes their footprint, assumes growth and proceeds with the direction to their real estate consultant to find 25,000 square foot alternatives in the marketplace. This can create costly problems if the user is in late stages of negotiations when it finds through the diligence of its design team that modern design efficiencies allow for greater use of space and ultimately a reduction in required office space, such that the necessary space may remain at 20,000 square feet. Thus, engaging the design team for early programming can save time, headaches and money.  The entire team benefits from early knowledge of the actual requirement and program.

A common method used for identifying critical milestone dates by the design, construction and real estate consultants, is to determine the desired occupancy date for “butts in seats”. What good is a space that has been deemed “substantially complete” if your business is not able to function in such a space? Working backward from the day that all systems are go with butts in seats, the design and construction team prepare the critical path schedule necessary to achieve the milestones for occupancy. Referring back to our sample user, the minimum time required to effectively perform the necessary steps is 34 weeks, on average, per the table below. However, in construction more than anything, it’s best to allow for contingencies where possible, and the more time one has for lease negotiation, the higher the probability for a better deal.

Tenant Relocation Process – Conceptual Time Line
Step Avg Time Allotment Cumulative Time
Programming 3 weeks 3 weeks
Identify Adequate Office Space 5 weeks 8 weeks
Create Short-List of  Options 1 weeks 8 weeks
Develop Test-Fit Plans 2 weeks 10 weeks
Preliminary Budgets and Schedules 2 weeks 12 weeks
Initiate Proposal & Conduct Lease Negotiations 6 weeks 18 weeks
Design, Permitting and Bidding (simultaneous) 6 weeks 24 weeks
Construction
12 weeks 36 weeks
Installation/Commissioning FF&E 2 weeks 38 weeks
Systems Commissioning and Certification 1 week 39 weeks
Occupancy – The typical schedule for a 20K SF office tenant to identify, design, build and occupy new space is approximately 39 weeks from start to finish (assuming no delays). 
Assumes that there are no changes or delays in approval process. Some of these steps can easily triple in time required if the process isn’t managed effectively.